George Bateman Brewery - Wainfleet
The project scope within this English brewery, founded in 1874, was to provide trace heating to the following systems: 

  • Stream 1 pipe line 15m, for Sodium Hydroxide - trace heating and lagging
  • Stream 2 pipe line 6m, for Sodium Hydroxide - trace heating and lagging
  • Stream 3 pipe line 20m, for nutrient - lagging only
  • Soium hyroxide dosing cabinet pipework 3m - trace heating and lagging
ESH supplied and installed the trace heating system to maintain the above pipework at +10C.